The refurbishment of three bridges over the M8 has been completed ahead of schedule.The work, which was carried out by Raynesway Construction, a subsidiary of Balfour Beatty, was finished 24 days before the end of a 75-day contract.The contract, carried ...
[Published Highways Magazine - May 13 2013]